"It's just hard to get here," Carys Wilkins told The Nugget in August. "You have to drive around a few laps to figure out how to get in." She and Benji Nagel run The Stand, the seasonal farm stand on Adams Avenue, and they spent the summer selling produce in the middle of a full street rebuild.
Those laps are over. On Friday, Oct. 23, the City of Sisters cut the ribbon on the finished Adams Avenue Streetscape at the corner of Ash Street and Adams, across from Sisters Artworks. Planners flagged a practical job for Adams in the city's original 2018 grant application: give drivers another way across town without funneling everyone onto Cascade Avenue, which is also Highway 20. November is the first full month the finished street can do that job, and the Holiday Palooza parade on Nov. 28 will be its first crowded downtown evening.
Eight Years From Open House to Ribbon Cutting
Adams has been on the city's list for a long time. Here's how the project moved, as The Nugget and the city told it:
| When | What happened |
|---|---|
| 2018 | A streetscape study funded by a state transportation grant. At an open house, 20 of 21 attendees picked the same design concept. |
| 2019 | City council approved that design. |
| 2020 to mid-2025 | The project sat on the shelf through the pandemic, other city priorities and funding gaps. |
| July 2025 | The Sisters Urban Renewal Agency voted to move forward. |
| Jan. to March 2026 | The job went out to bid. Bids opened Feb. 25, and in March the council awarded the contract to Deschutes Construction Corp. |
| Summer 2026 | Construction, with lighting going in last in mid-October. |
| Oct. 23, 2026 | Ribbon cutting at Ash and Adams. |
The work covered Adams Avenue's 80-foot-wide right-of-way from Cedar Street to Pine Street. It also rebuilt parts of the side streets that run between Adams and Main. Those side streets are why the project matters for anyone headed downtown. They connect the new parking and sidewalks on Adams straight to Main Avenue.
What's on the Street Now
City Manager Jordan Wheeler described the old Adams to Central Oregon Daily this way: "The street didn't have any sidewalks, didn't have any parking. It was hard to navigate. A lot of people had to walk in the road." Here's what replaced it:
| Before the rebuild | After the rebuild |
|---|---|
| No sidewalks, so people walked in the road | New concrete sidewalks and wider asphalt paths shared by walkers and cyclists |
| No on-street parking | Added on-street parking |
| A rough edge of downtown | About 200 new street trees, plus decorative circles at the intersections |
| Overhead power and a drain-rock swale | Underground electrical work and stormwater upgrades |
| Dim at night | New street lighting |
The design choice people have talked about most is the shared path. The city skipped standard bike lanes and widened the sidewalks so people walking and people biking use the same path. City officials told The Nugget that this cuts the distance a person has to cross the road by close to a third, and it slows traffic too. Not everyone is convinced. At least one letter to the paper asked whether mixing bikes and foot traffic could cause problems for kids, older residents, and people using wheelchairs or walkers. The first busy evening on the new paths should start to answer that.
Mayor Jennifer Letz told The Nugget what she expects from the finished street:
"New sidewalks and paths will increase bike and pedestrian safety and make the street more accessible for those with mobility challenges. There will be more parking, and dozens of new trees and plants will provide shade and gussy up the street."
Sources don't agree on the intersection circles. The Nugget's August story counted seven, while the city's bid schedule lists six. A walk from Pine to Cedar will settle it faster than any document.
The Same Money That Built Fir Street Park
Most of the money came from the Sisters Urban Renewal Agency. The agency is funded by the extra property tax revenue downtown produces as assessed values there rise. That same source has paid for work on Cascade and Hood avenues, Fir Street Park and other downtown projects. Put simply, downtown's own growth paid for its newest street.
The price changed as the project moved along. In 2021 the city estimated $4 million, to be paid from street system development charges, urban renewal funds and developer contributions. The engineer's estimate in the 2026 bid documents was $3,123,000. The contract the council awarded in March came in at just under $3.55 million. That was more than the bid estimate and less than the 2021 figure.
City leaders have said what they hope that money buys. Letz explained to The Nugget that "since Adams has lacked sidewalks and parking, this has stymied any building or development," and that urban renewal dollars went into the corridor to encourage new businesses and homes. The corridor has businesses on its west end and homes to the east. Any new building will take years to show up. The sidewalk, the parking and the lights are already there.
The Businesses That Stayed Open Through the Summer
The summer was hard for some neighbors on the corridor, and The Nugget reported concerns from local business owners about access during construction. The Stand's operators said their business was down this summer. They also praised the construction crew for working to keep the space in front of the stand open, and Wilkins added, "Everybody has been so kind."
Those businesses carried the cost of construction before anyone got to use the finished street. Here's who to look for now that it's open:
- Sisters Artworks, across from the ribbon-cutting corner at Ash and Adams.
- Three Sisters Floral at 243 N. Elm St., a florist worth remembering when holiday arrangements go on the list.
- The Stand at 254 E. Adams Ave. It sells farm produce from early May through the end of October, according to Travel Oregon, so it's done for 2026. Next May will be its first full season on the finished street.
A Back Way to the Tree Lighting
The first real test comes Saturday, Nov. 28. Sisters Park & Recreation District's Holiday Palooza Parade & Tree Lighting runs from 3:30 to 5:30 p.m. The parade goes down East Main Avenue, and the activities and tree lighting are at Fir Street Park, 150 N. Fir St. Fir Street Park was paid for by the same urban renewal fund as the new street.
This is the first Holiday Palooza with the rebuilt street in place, and it changes how you can get there:
- Come in on Adams. It runs east-west along the north edge of downtown and keeps you off Highway 20 for the last stretch.
- Park on the new on-street parking, which Adams didn't have before this year.
- Walk down a rebuilt side street. The rebuild included the side streets between Adams and Main, and The Nugget's August update said new sidewalks were going in on those streets from Oak to Fir.
- Head back under the new lights. The festivities end at 5:30 on a late-November evening, and lighting was the last part of the project to go in.